40-meter-long Channel in Cijantung Attached with Manhole Covers
access_time January 16 2025 02:42 PM remove_red_eye 164
Reported by Nurito | Translated by Nugroho Adibrata
Reported by Nurito | Translated by Nugroho Adibrata
Ten personnel from the Pasar Rebo Sub-district Water Resources Task Force, attached the manhole covers in the channel as long as 40 meters on Jalan Asem, RT 03/01, Cijantung Urban Village.
Surely, residents will feel safe and comfortable
Pasar Rebo Sub-district SDA Executing Unit Head, Nana Juhana said the channel on Jalan Asem was covered with with a 40-centimeter concrete slab for the safety and comfort of residents.
"This work has been ongoing since January 7 and is targeted to be completed on January 31," she expressed, Thursday (1/16).
Damaged Manhole Cover at Pasar Minggu Underpass RepairedThe action above received appreciation from Cijantung Urban Village Head, Teguh Suharyono.
"Surely, residents will feel safe and comfortable," he concluded.